Works on this project initially began with the demolition of a disused warehouse building on site. The Ashford Baptist Church had purchased the building with the intention of refurbishing it to form a new centre for their church, however after completing initial works it became clear this was not cost effective and instead employed Borras to construct a new purpose-build facility.

Demolition works were carried out with the utmost care due to the close proximity of nearby properties and included the part demolition of a wall shared between the existing warehouse and a neighbouring building.

Once demolition and site clearance work was complete the new steel framed structure with mezzanine floor was erected. The ground floor of the building features underfloor heating and provides a multi purpose room, office, toilets, kitchen and a large Worship Hall. A 4 foot deep Baptistery pool is sunken into the floor of the Worship Hall that can be covered when not in use (pictured above).

The mezzanine floor features 4 group rooms, additional toilets and a balcony which over looks the Worship Hall. Externally, solar panels were fitted to the roof and new access roads were formed along with new parking at the front and rear of the building.

Community Projects

White Lion Square Regeneration

At Borras Construction, engaging with local communities is at the heart of what we do. This project in…

Camberwell New Cemetery Lodge Refurbishment

At Borras Construction, we’re committed to delivering works efficiently, whilst understanding the vision of our clients and their…

Garthwaite Sports and Community Pavilion

This project, carried out in partnership with Shenley Brook End and Tattenhoe Parish Council, involved extensive research, planning…

West Ham United FC Academy

At Borras Construction, we’re committed to delivering works efficiently, whilst understanding the vision of our clients and their…

Woodlands Community

At Borras Construction, we’re committed to delivering works efficiently, whilst understanding the vision of our clients and their…

White Lion House

This project formed part of the Council’s larger investment programme aiming to create a better environment for shoppers,…

Shenley Brook End & Tattenhoe Parish Council Offices

Completed by our Special Works team in July 2016, this scheme involved the construction of a new headquarters…

Welwyn Hatfield Council Chamber

This project involved the creation and fit out of Welwyn Hatfield Borough Council's first ever purpose built Council…

Palmers Green Library

This project on behalf of the London Borough of Enfield saw the complete refurbishment of Palmers Green Library.…

Church House Hendon

Completed by our Special Works Division in June 2016, this project involved extensive refurbishment works to Church House…

Pound Close Community Centre

This project, which was completed in April 2016 by our Special Works Division, involved the construction of a…

Chesham Opportunities Centre

Borras Construction were awarded this project to construct a new day centre on behalf of Buckinghamshire County Council…